Skip to Main Content
Text:  A  A  A
GFE Feasibility Study for Redeveloping Goodison Park
Phasing Logistics

Phase One    +/- Capacity  
         
     

40,179

 
  Demolish Bullens Road Stand

-10,759

 
      29,420 Start of Season
  Rebuild New Stand - Lower Tier   7,600  
      37,020 end September
   Complete New Stand 6,650  
      43,670 end February
         
Phase Two        
         
      43 670  
  Demolish Goodison Road Stand  - 12 402  
      31 268 Start of Season
  Rebuild New Stand - Lower Tier  + 7 600  
      38 868 end September
   Complete New Stand  + 6 650  
      45 518 end February
         
Phase Three        
         
      45 518  
  Demolish Gwladys St Stand  - 11 052  
      34 466 Start of Season
  Rebuild New Stand - Lower Tier  + 5 760  
      40 226 end August
   Complete New Stand  + 4 990  
      45 216 end January
         
Phase Four        
         
      45 216  
  Demolish Park End Stand  - 5 996  
      39 250 Start of Season
  Rebuild New Stand - Lower Tier  + 5 760  
      45 010 end August
   Complete New Stand  + 4 990  
      50 000 end January

The above phasing plan allows for the Ground to be fully redeveloped in 3.75 years from start to finish. It would be possible, however, to achieve full redevelopment in 2.75 years by combining Phase 3 and Phase 4, ie the short sides of the Ground, and carrying out the work simultaneously would provide the following capacities:

Phase Three    +/- 45 518  
  Demolish Gwladys St Stand  - 11 052  
  Demolish Park End Stand  - 5 996  
      28 500 Start of Season
  Rebuild New Stands - Lower Tiers  + 11 520  
      40 020 end September
  Complete New Stands   9 980  
      50 000 end February


« Previous Index Next »


OK

We use cookies to enhance your experience on ToffeeWeb and to enable certain features. By using the website you are consenting to our use of cookies in accordance with our cookie policy.